Work on a construction or precast project doesn’t stop when an inspection request comes back with comments. The site team fixes the problem, and then it’s on the document controller to send a close-out that the consultant can review quickly. If that paperwork is messy, an issue that’s already fixed can stay open for weeks.
This is the routine I use for a commented or rejected Material or Work Inspection Request (MIR/WIR).
1. Read the comments before touching the file
First I read every comment the consultant wrote, word for word, and note exactly what they asked for: a repair, a re-check of alignment, an updated test report, a missing signature. I also confirm with the site or QC engineer that the work has actually been done. Closing out on paper something that isn’t fixed on site only brings the same comment back.
2. Prepare the revised copy
I start from the returned request, not from a blank form, so the reference number, description and location stay exactly the same. Then I:
- Raise the revision by one (00 becomes 01, 01 becomes 02)
- Remove the old inspection date and any notes that only applied to the first submission
- Mark the subject or description clearly as a close-out, so nobody has to guess what this copy is for
3. Attach the right evidence for each comment
Every comment needs its own answer. For repairs it’s usually a signed checklist or a record of the corrective work. I keep a small library of standard checklist pages, one for each type of comment we see often, so I can match them quickly. The submittal reference and description on the checklist must match the request exactly. One wrong digit is enough for the package to be returned again.
4. Name it, log it, submit it
I name the file to the project’s naming convention, including the new revision, and upload it to the document management system as a new revision of the same request. A new standalone document would break the history. Then I update the register with the resubmission date and status, so I can follow up if the review takes longer than the agreed turnaround.
Why it matters
None of these steps is complicated, but skipping one of them is what keeps an item open. A clean close-out means the consultant can approve it on the first read, the record shows a clear trail from comment to fix, and the handover file is in order at the end of the project.
If you work in document control, what’s in your close-out routine? I’d be glad to hear what other people do.