Our 30/11 kV distribution project covers five identical substations. Each site already has a Siemens Substation Control Center running on WinCC that is only partially configured. The control center exchanges data with an A8000 RTU over IEC 60870-5-104, while the RTU speaks IEC 61850 to the Siemens protection IEDs. I now need a specialist who can take the existing configuration and drive it through to full, reliable operation. That involves: • Configuring and fine-tuning the IEC 104 link between SCC and A8000. • Verifying and, where needed, correcting the IEC 61850 data mapping between RTU and IEDs. • Completing the WinCC screen and tag setup so that all breaker, measurement and alarm points display and archive correctly. • Running end-to-end tests—point checks, sequence of events, failover and power-up—to prove the system before energization. • Delivering each substation’s final, documented WinCC project along with a concise commissioning report and any modified SCD/CID files. I can supply the present WinCC projects, IEC 61850 SCD files and remote access (VPN) to the RTUs for off-site work. Site teams are ready to follow your instructions for loop-back tests, wiring checks and any local patch loading you direct. Success for me is simple: every tag updates with the correct time-stamps, all commands operate first time, alarms appear in the right priority and the five substations share a uniform, stable HMI that operations can rely on from day one. If you have proven experience with Siemens WinCC in substation environments and are comfortable leading a remote-commissioning effort, I look forward to working with you.
Project ID: 40683909
26 proposals
Remote project
Active 3 days ago
Set your budget and timeframe
Get paid for your work
Outline your proposal
It's free to sign up and bid on jobs
26 freelancers are bidding on average $3,896 USD for this job

Having studied Electrical Engineering and specializing in firmware development, I'm confident I am the right choice to complete your Siemens SCC HMI commissioning project. My expertise in industrial automation with deep experience setting up SCADA and HMI systems will be truly beneficial for this task. I have a proven track record of configuring and fine-tuning connectivity protocols such as IEC 104 and 61850, as well as ensuring seamless data mapping. My proficiency with WinCC coupled with an in-depth understanding of substation environments places me in a prime position to tackle this project head-on. I'm equipped with extensive skills including designing advanced PCB layouts and RF hardware that can be useful for effective integration and establishing reliable communication between the SCC, A8000 RTUs, and Siemens protection IEDs. I adhere to a meticulous approach where no detail is overlooked, especially when running end-to-end tests for optimal system performance. My results-driven mindset guarantees every tag will update accurately, breakers will function correctly, alarms will appear as required, and the substations will be left with a uniform, stable HMI system, fully documented along with your desired commissioning report. Let's collaborate on this project and achieve seamless operations right from day one for each of the five substations.
$4,000 USD in 30 days
8.2
8.2

Greetings! I can complete the configuration and commissioning of your Siemens Substation Control Center across all five substations. I would fine tune the IEC 104 link between the SCC and A8000 RTU, verify and correct the IEC 61850 data mapping between the RTU and protection IEDs, and complete the WinCC screen and tag setup for all breaker, measurement, and alarm points. I would run end to end tests including point checks, sequence of events, failover, and power up to prove the system. I would deliver final WinCC projects, commissioning reports, and modified SCD or CID files for each substation. I have experience with Siemens WinCC in substation environments and can lead remote commissioning with your site teams. Let me know your preferred start date and I can get started. Thanks, Revival
$3,000 USD in 30 days
6.3
6.3

HI, KINDLY READ THROUGH MY PROPOSAL I will complete and commission the Siemens Substation Control Center (WinCC) configuration for your five identical 30/11 kV substations, bringing the IEC 104 link, IEC 61850 mapping and HMI to full, reliable operation. MY APPROACH ✅ Configure and fine-tune the IEC 60870-5-104 link between SCC and A8000 RTU ✅ Verify and correct IEC 61850 data mapping between RTU and protection IEDs ✅ Complete WinCC screens, tags, archiving and alarm handling for a uniform HMI ✅ Lead end-to-end testing (point checks, SOE, failover, power-up) with remote guidance to site teams ✅ Deliver final documented WinCC projects, modified SCD/CID files and commissioning reports DELIVERABLES - Fully working and uniform WinCC projects for all five substations - Updated SCD/CID files if required - Concise commissioning report per substation QUESTIONS 1. Can you share the current WinCC projects and IEC 61850 SCD files? 2. Is VPN remote access to the RTUs already available? Ready to start immediately.
$3,000 USD in 3 days
6.4
6.4

I understand you require assistance in bringing your Siemens SCC HMI configuration to full operational status, similar to how I've provided Technical Support for complex system integrations. My focus will be on ensuring the seamless data flow and accurate representation of your substation assets. My approach involves a systematic verification of the existing IEC 60870-5-104 configuration between the SCC and the A8000 RTU. I will diagnose and resolve any communication errors, optimizing parameters for reliable data exchange. For the IEC 61850 data mapping, I will meticulously review the current setup, identifying any discrepancies and implementing necessary corrections to ensure precise data translation between the RTU and the Siemens protection IEDs. My expertise in Technical Support allows me to troubleshoot and resolve such connectivity and configuration challenges. Could you clarify the current documentation available for the existing SCC and A8000 configurations? Additionally, are there specific performance metrics or uptime requirements you are targeting for the commissioned system? I am available to discuss your project in more detail at your convenience.
$4,432 USD in 21 days
5.1
5.1

Having gathered extensive experience over the years in similar projects to yours, I am more than equipped to be of immense value to your Siemens SCC HMI Commissioning project. I have a deep understanding of Siemens WinCC and have used it across different environments including wastewater treatment plants, water treatment plants, and even in the iron steel industry using Honeywell DCS C200. With Siemens WinCC and other Siemens tools such as Simatic Manager and TIA Portal forming a significant part of my toolbox, I can guarantee seamless configuration and fine-tuning of the IEC 104 link between SCC and A8000 as well as verifying and correcting the IEC 61850 data mapping between RTU. A key aspect that sets me apart is my proven ability to work remotely while successfully leading commissioning efforts. Moreover, my technical aptitude extends further to other critical areas such as point-to-point tests, failover and power-up sequences- skills that will allow me to comprehensively prove the system before energization. Trust me with your project, and every tag will update with correct timestamps, every command will operate as expected, alarms will appear in the correct priority order, and overall ensure uniformity across the five substations- all these being focal points for your project. In addition to my extensive capabilities, you can rely on me for prompt report generation (SCD/CID files) encompassing all project specifics alongside
$4,000 USD in 7 days
5.0
5.0

Hi, your project is about taking an already-partial Siemens SCC setup and finishing it into a stable, fully tested substation HMI across five identical sites. I’ve worked on Siemens WinCC-based industrial and substation interfaces, including IEC 60870-5-104 links, tag configuration, alarm handling, and commissioning support. That experience helps when the challenge is not building from scratch, but tightening an existing system so it behaves consistently. My approach would be to review the current WinCC project and SCD/CID files, verify the IEC 104 and IEC 61850 mappings, then correct the tag, screen, timestamp, and archive setup. After that I’d run point checks, SOE validation, failover, and power-up tests with your site teams until each station is ready for energization. If you’d like, I can help bring the five substations to one reliable standard. Best regards, Gabriel
$3,000 USD in 30 days
4.3
4.3

I have extensive experience with Siemens WinCC in substation environments, familiar with configuring IEC 104 links and optimizing IEC 61850 data mapping for reliable operations. I will conduct comprehensive testing, finalize WinCC setup, and collaborate closely with site teams for successful project completion. My goal is to ensure accurate tag updates, flawless commands, prioritized alarms, and standardized HMIs across all substations. I am committed to delivering a reliable system through meticulous attention to detail. I look forward to collaborating with you to bring this project to completion and establish a long-term partnership for maintenance and support. Thank you for considering my expertise for this essential commissioning effort.
$4,500 USD in 5 days
4.1
4.1

I have over ten years of experience configuring and commissioning Siemens WinCC SCADA systems in substation environments. I am confident I can bring each of the five identical substations to full, reliable operation by fine‑tuning the IEC‑104 link to the A8000 RTU, validating the IEC‑61850 data mapping, completing the WinCC screens and tag sets, and executing comprehensive end‑to‑end tests—including point checks, event sequences, fail‑over, and power‑up procedures—remotely via VPN. I will deliver fully documented WinCC projects, updated SCD/CID files, and concise commissioning reports that guarantee accurate timestamps, first‑time command execution, and correctly prioritized alarms, ensuring a uniform, stable HMI ready for day‑one operations.
$3,000 USD in 7 days
2.7
2.7

Hello, As a seasoned architect and a project management specialist, I have a keen understanding of the importance of effective HMI commissioning in critical infrastructure like substations. I have worked with complex systems like Siemens WinCC extensively and am well versed with configuring IEC protocols (104 & 61850) as well. In addition, my skills in visualizing architectural blueprints to create immersive experiences will come in handy while completing the WinCC setup for your substations. Also, having lead numerous remote-commissioning efforts before, I am familiar with the potential challenges and successful practices that come with such projects. Finally, my offer stands on thorough end-to-end testing to ensure full reliability and delivering comprehensive documentation. You can rest assured that every task will be completed to an impeccable standard for when it's time to energize these substations, offering your operations team the uniform, stable HMI system they can rely on from day one. Let's transfer your commissioning vision into an outstanding reality! Thanks!
$4,440 USD in 6 days
3.0
3.0

I appreciate the detailed overview of your project and the clear expectations you have for achieving full operational capability. I have successfully completed similar projects, specifically working with Siemens WinCC in substations, where I managed the commissioning of control centers and ensured seamless data integration with RTUs. Your goal of ensuring a reliable HMI across five substations resonates with me; I understand the critical importance of accuracy and stability in such environments. I’m particularly interested in the configuration of the IEC 104 link and ensuring that all alarms and measurements are correctly displayed and archived in WinCC. With extensive experience in performance tuning, data security, and enhancing user experience, I can ensure that each tag updates accurately and commands execute flawlessly. Could we discuss how my approach might align with your specific needs for this project? Best regards, Foraxis
$3,500 USD in 7 days
1.4
1.4

Hey, Based on your requirements, I understand that you need the five identical 30/11 kV substations taken from their partially configured Siemens WinCC/SCC state through complete, reliable commissioning, including IEC 60870-5-104 communication with the A8000 RTU and IEC 61850 mapping to the protection IEDs. You mentioned that you can provide the current WinCC projects, IEC 61850 SCD files, and VPN access to the RTUs. Having these available at the start will allow the existing configuration and mappings to be reviewed before making changes. Questions: - Is there a master I/O/tag list defining the expected breaker, measurement, alarm, command, and status points for all five substations? - Are the five substations already using a common WinCC project/template, or should the validated configuration from the first site become the baseline for the remaining four? - What redundancy/failover architecture is currently implemented for the SCC, RTU, and network communication paths? Further discussions and analysis will be exchanged once we are aligned on the same page. MH from Royal Designs Budget and timeframe are placeholders.
$3,000 USD in 7 days
0.0
0.0

✋ Hi, this requires someone who is comfortable with substation automation, not just general WinCC configuration. I’d first verify the IEC 104 communication and point mapping between SCC and A8000, then trace the IEC 61850 data through to the IEDs before correcting tags, alarms, measurements, and commands in WinCC. After that, I’d run structured end-to-end checks for timestamps, SOE, failover, power-up, and command reliability across all five substations. Do you already have the current IEC 104 point list and the latest SCD/CID files for each site?
$3,500 USD in 10 days
0.0
0.0

Hello, The first priority should be validating the communication and data model before finishing the HMI screens. I’d review IEC 104 addressing, IEC 61850 mappings, WinCC tags, alarms, commands, and timestamps as one connected chain, then commission one substation fully as the reference configuration before standardizing the remaining four. Are the five substations truly identical at the IED and point-list level, or are there site-specific differences that need separate mapping? Thanks
$5,000 USD in 10 days
0.0
0.0

Rahul here... Having worked as a Full-Stack Developer for over a decade, my skill set is broad yet specialized, with a key focus on automation and project management. I believe that these skills align perfectly with your need for advancing the existing Siemens Substation Control Centers. I am well-versed in Siemens WinCC and understand the intricacies of substation environments thoroughly. My experience includes working with IEC104 and IEC61850 protocols, configuring and maintaining stable HMIs, and running comprehensive system tests - all vital tasks for your project. One of the attributes that sets me apart is my ability to comprehend complex ideas and devise simplified yet functional solutions. This characteristic could prove especially beneficial as we work together remotely during this commissioning effort. I'm skilled in using collaboration tools like VPNs effectively to ensure seamless off-site work. Moreover, my previous projects have equipped me with robust problem-solving skills in relation to time-stamps, command operating systems, alarms prioritizing accurately, and unison HMIs - all factors crucial for your project's success. By entrusting me with your project, you can expect not only precise completion of said tasks but also timely finalization of each substation's clean-cut WinCC project along with a comprehensive commissioning report to ensure a reliable HMI from day one.
$3,500 USD in 21 days
0.0
0.0

As an experienced IT specialist with a strong background in automation, I believe I am the perfect fit for your Siemens SCC HMI Commissioning project. Over the course of my 9+ years career, I've honed my skills in web and mobile development, an area that requires a deep understanding of systems and their connections. Plus, having provided similar services to various industrial sectors, I understand the specific needs that a comprehensive substation control system such as yours requires. My ability to configure and fine-tune complex systems such as the IEC 104 link and IEC 61850 data mapping aligns neatly with your needs. I'm patient when it comes to meticulous tasks like verifying and correcting data, ensuring no detail is overlooked. Conducting end-to-end tests is also something I excel at - providing you peace of mind that your system runs efficiently before full operation. Moreover, choosing me for this job isn't just about my technical expertise; it's about benefiting from a well-rounded professional who understands the full scope of your project. Not only will I provide you with carefully documented WinCC projects, but also a detailed commissioning report to help you analyze the project efficacy. My after-sales support commitment adds extra value to my service, ensuring smooth operations even after project completion. With me leading the charge for your remote commissioning effort, rest assured all the five substations will share a stable HMI that your oper
$4,000 USD in 7 days
0.0
0.0

Tripoli, Libya
Member since Sep 1, 2026
$250-750 USD
$30-250 USD
$10-30 USD
₹12500-37500 INR
₹12500-37500 INR
₹12500-37500 INR
$30-250 AUD
$3000-5000 USD
$30-250 USD
₹12000-20000 INR
₹1500-12500 INR
₹12500-37500 INR
$250-750 USD
min ₹2500 INR / hour
$3000-5000 USD
₹1500-12500 INR
$1000-2000 USD
₹1500-12500 INR
₹1500-12500 INR
$8-15 USD / hour